UUFA Solar Project Update

UUFA’s solar project is going extremely well.  Solar Sun World made wonderful preparations and calculations, which are paying handsome dividends during installation.

All solar panels and inverters are installed.  Wiring and hookups to the inverters and electricals in the mechanical room will be the next steps.  Once installation is complete, the system will be tested.  An internet connection will allow us to use our phones and computers to monitor electricity production.  All of this is expected to be finished before Memorial Day.

Within a week or so of Solar Sun World finishing, we hope that Clarke County and Georgia Power will inspect our project.  Also, our existing meter will be reprogrammed, giving us the green light we have been waiting for.

Putting all this together, we expect our solar equipment to produce electricity in early June.

——————————————————————————